4.06     The Board shall, within 30 days or at the next public meeting for which notice can be given, review the application for completeness as required by these Regulations. If the application is determined to be complete and all required fees have been paid,  then the Board shall by motion accept the application as complete relative to the jurisdiction of the Board per RSA 676:4 i(b) and begin formal consideration of the application

 

            If the Board finds the application to be incomplete, the subdivider shall be notified of the deficiencies in writing. The Board may reject an application with no further action based upon failure to supply information required by the Regulations, failure to meet reasonable deadlines established by the Board, or failure to pay cost of notice or other fees required by the Board.

 

            The Planning Board will approve, conditionally approve or disapprove within 65 days after formal acceptance in accordance with RSA 676:4.  Conditional approval shall become final without further public hearing upon certification to the Planning Board of compliance with the conditions imposed, provided however, that the conditions meet the requirements of RSA 676:4.  All other conditions require a public hearing.

 

  1. The board shall, at the next regular meeting or within 30 days following the delivery of the application, for which notice can be given in accordance with the requirements of subparagraph (b), determine if a submitted application is complete according to the board's regulation and shall vote upon its acceptance. Upon determination by the board that a submitted application is incomplete according to the board's regulations, the board shall notify the applicant of the determination in accordance with RSA 676:3, which shall describe the information, procedure, or other requirement necessary for the application to be complete. Upon determination by the board that a submitted application is complete according to the board's regulations, the board shall begin formal consideration and shall act to approve, conditionally approve as provided in subparagraph (i), or disapprove within 65 days, subject to extension or waiver as provided in subparagraph (f). In the case of a determination by the board that the application is a development of regional impact requiring notice in accordance with RSA 36:57, III, the board shall have an additional 30 days to act to approve, conditionally approve, as provided in subparagraph (i), or disapprove. If the board determines that it lacks sufficient information to make a final decision on an application and the applicant does not consent to an extension pursuant to subparagraph (f), the board may, in its discretion, deny the application without prejudice, in which case the applicant may resubmit the same or a substantially similar application. If the planning board does not act on the application within that 65-day time period, then the selectmen or city council shall certify on the applicant's application that the plat is approved pursuant to this paragraph. Such a certification, citing this paragraph, shall constitute final approval for all purposes including filing and recording under RSA 674:37 and 676:18, and court review under RSA 677:15.
  2. Failure of the selectmen or city council to certify approval of the plat upon the planning board's failure to act within the required time period shall constitute grounds for the superior court, upon petition of the applicant, to issue an order approving the application. The superior court shall act upon such a petition within 30 days. If the court determines that the failure of the selectmen or the city council to act was not justified, the court may order the municipality to pay the applicant's reasonable costs, including attorney's fees, incurred in securing such order.

 

676:4 I(f)

(90 Day Extension Eliminated)

8/23/22

4.10     The Planning Board may apply to the Selectmen for an extension not to exceed an additional 90 days before acting to approve or disapprove an application.  The applicant may waive the requirement for Planning Board action within the time periods specified in Section 4.06 and consent to such extension as may be mutually agreeable

The applicant may waive the requirement for planning board action within the time periods specified in subparagraph (c) and consent to such extension as may be mutually agreeable.

673:3, I

(Written Findings)

8/23/22

None

The local land use board shall issue a final written decision which either approves or disapproves an application for a local permit and make a copy of the decision available to the applicant. The decision shall include specific written findings of fact that support the decision. Failure of the board to make specific written findings of fact supporting a disapproval shall be grounds for automatic reversal and remand by the superior court upon appeal, in accordance with the time periods set forth in RSA 677:5 or RSA 677:15, unless the court determines that there are other factors warranting the disapproval. If the application is not approved, the board shall provide the applicant with written reasons for the disapproval. If the application is approved with conditions, the board shall include in the written decision a detailed description of all conditions necessary to obtain final approval.

 

673:16, III

(Publication of Fees)

8/23/22

None

II. Any fee which a city or town imposes on an applicant pursuant to this title shall be published in a location accessible to the public during normal business hours. Any fee not published in accordance with this paragraph at the time an applicant submits an application shall be considered waived for purposes of that application. A city or town may comply with the requirements of this section by publicly posting a list of fees at the city or town hall or by publishing a list of fees on the city or town's Internet website.

 

 

 

RSA

Effective Date

Previous Language

New or Revised Language

676:4I(c)

(Planning Board Timeline)

1/01/23

4.06     The Board shall, within 30 days or at the next public meeting for which notice can be given, review the application for completeness as required by these Regulations. If the application is determined to be complete and all required fees have been paid,  then the Board shall by motion accept the application as complete relative to the jurisdiction of the Board per RSA 676:4 i(b) and begin formal consideration of the application

 

            If the Board finds the application to be incomplete, the subdivider shall be notified of the deficiencies in writing. The Board may reject an application with no further action based upon failure to supply information required by the Regulations, failure to meet reasonable deadlines established by the Board, or failure to pay cost of notice or other fees required by the Board.

 

            The Planning Board will approve, conditionally approve or disapprove within 65 days after formal acceptance in accordance with RSA 676:4.  Conditional approval shall become final without further public hearing upon certification to the Planning Board of compliance with the conditions imposed, provided however, that the conditions meet the requirements of RSA 676:4.  All other conditions require a public hearing.

 

  1. The board shall, at the next regular meeting or within 30 days following the delivery of the application, for which notice can be given in accordance with the requirements of subparagraph (b), determine if a submitted application is complete according to the board's regulation and shall vote upon its acceptance. Upon determination by the board that a submitted application is incomplete according to the board's regulations, the board shall notify the applicant of the determination in accordance with RSA 676:3, which shall describe the information, procedure, or other requirement necessary for the application to be complete. Upon determination by the board that a submitted application is complete according to the board's regulations, the board shall begin formal consideration and shall act to approve, conditionally approve as provided in subparagraph (i), or disapprove within 65 days, subject to extension or waiver as provided in subparagraph (f). In the case of a determination by the board that the application is a development of regional impact requiring notice in accordance with RSA 36:57, III, the board shall have an additional 30 days to act to approve, conditionally approve, as provided in subparagraph (i), or disapprove. If the board determines that it lacks sufficient information to make a final decision on an application and the applicant does not consent to an extension pursuant to subparagraph (f), the board may, in its discretion, deny the application without prejudice, in which case the applicant may resubmit the same or a substantially similar application. If the planning board does not act on the application within that 65-day time period, then the selectmen or city council shall certify on the applicant's application that the plat is approved pursuant to this paragraph. Such a certification, citing this paragraph, shall constitute final approval for all purposes including filing and recording under RSA 674:37 and 676:18, and court review under RSA 677:15.
  2. Failure of the selectmen or city council to certify approval of the plat upon the planning board's failure to act within the required time period shall constitute grounds for the superior court, upon petition of the applicant, to issue an order approving the application. The superior court shall act upon such a petition within 30 days. If the court determines that the failure of the selectmen or the city council to act was not justified, the court may order the municipality to pay the applicant's reasonable costs, including attorney's fees, incurred in securing such order.

 

676:4 I(f)

(90 Day Extension Eliminated)

8/23/22

4.10     The Planning Board may apply to the Selectmen for an extension not to exceed an additional 90 days before acting to approve or disapprove an application.  The applicant may waive the requirement for Planning Board action within the time periods specified in Section 4.06 and consent to such extension as may be mutually agreeable

The applicant may waive the requirement for planning board action within the time periods specified in subparagraph (c) and consent to such extension as may be mutually agreeable.

673:3, I

(Written Findings)

8/23/22

None

The local land use board shall issue a final written decision which either approves or disapproves an application for a local permit and make a copy of the decision available to the applicant. The decision shall include specific written findings of fact that support the decision. Failure of the board to make specific written findings of fact supporting a disapproval shall be grounds for automatic reversal and remand by the superior court upon appeal, in accordance with the time periods set forth in RSA 677:5 or RSA 677:15, unless the court determines that there are other factors warranting the disapproval. If the application is not approved, the board shall provide the applicant with written reasons for the disapproval. If the application is approved with conditions, the board shall include in the written decision a detailed description of all conditions necessary to obtain final approval.

 

673:16, III

(Publication of Fees)

8/23/22

None

II. Any fee which a city or town imposes on an applicant pursuant to this title shall be published in a location accessible to the public during normal business hours. Any fee not published in accordance with this paragraph at the time an applicant submits an application shall be considered waived for purposes of that application. A city or town may comply with the requirements of this section by publicly posting a list of fees at the city or town hall or by publishing a list of fees on the city or town's Internet website.

 

 

 

RSA

Effective Date

Previous Language

New or Revised Language

676:4I(c)

(Planning Board Timeline)

1/01/23

4.06     The Board shall, within 30 days or at the next public meeting for which notice can be given, review the application for completeness as required by these Regulations. If the application is determined to be complete and all required fees have been paid,  then the Board shall by motion accept the application as complete relative to the jurisdiction of the Board per RSA 676:4 i(b) and begin formal consideration of the application

 

            If the Board finds the application to be incomplete, the subdivider shall be notified of the deficiencies in writing. The Board may reject an application with no further action based upon failure to supply information required by the Regulations, failure to meet reasonable deadlines established by the Board, or failure to pay cost of notice or other fees required by the Board.

 

            The Planning Board will approve, conditionally approve or disapprove within 65 days after formal acceptance in accordance with RSA 676:4.  Conditional approval shall become final without further public hearing upon certification to the Planning Board of compliance with the conditions imposed, provided however, that the conditions meet the requirements of RSA 676:4.  All other conditions require a public hearing.

 

  1. The board shall, at the next regular meeting or within 30 days following the delivery of the application, for which notice can be given in accordance with the requirements of subparagraph (b), determine if a submitted application is complete according to the board's regulation and shall vote upon its acceptance. Upon determination by the board that a submitted application is incomplete according to the board's regulations, the board shall notify the applicant of the determination in accordance with RSA 676:3, which shall describe the information, procedure, or other requirement necessary for the application to be complete. Upon determination by the board that a submitted application is complete according to the board's regulations, the board shall begin formal consideration and shall act to approve, conditionally approve as provided in subparagraph (i), or disapprove within 65 days, subject to extension or waiver as provided in subparagraph (f). In the case of a determination by the board that the application is a development of regional impact requiring notice in accordance with RSA 36:57, III, the board shall have an additional 30 days to act to approve, conditionally approve, as provided in subparagraph (i), or disapprove. If the board determines that it lacks sufficient information to make a final decision on an application and the applicant does not consent to an extension pursuant to subparagraph (f), the board may, in its discretion, deny the application without prejudice, in which case the applicant may resubmit the same or a substantially similar application. If the planning board does not act on the application within that 65-day time period, then the selectmen or city council shall certify on the applicant's application that the plat is approved pursuant to this paragraph. Such a certification, citing this paragraph, shall constitute final approval for all purposes including filing and recording under RSA 674:37 and 676:18, and court review under RSA 677:15.
  2. Failure of the selectmen or city council to certify approval of the plat upon the planning board's failure to act within the required time period shall constitute grounds for the superior court, upon petition of the applicant, to issue an order approving the application. The superior court shall act upon such a petition within 30 days. If the court determines that the failure of the selectmen or the city council to act was not justified, the court may order the municipality to pay the applicant's reasonable costs, including attorney's fees, incurred in securing such order.

 

676:4 I(f)

(90 Day Extension Eliminated)

8/23/22

4.10     The Planning Board may apply to the Selectmen for an extension not to exceed an additional 90 days before acting to approve or disapprove an application.  The applicant may waive the requirement for Planning Board action within the time periods specified in Section 4.06 and consent to such extension as may be mutually agreeable

The applicant may waive the requirement for planning board action within the time periods specified in subparagraph (c) and consent to such extension as may be mutually agreeable.

673:3, I

(Written Findings)

8/23/22

None

The local land use board shall issue a final written decision which either approves or disapproves an application for a local permit and make a copy of the decision available to the applicant. The decision shall include specific written findings of fact that support the decision. Failure of the board to make specific written findings of fact supporting a disapproval shall be grounds for automatic reversal and remand by the superior court upon appeal, in accordance with the time periods set forth in RSA 677:5 or RSA 677:15, unless the court determines that there are other factors warranting the disapproval. If the application is not approved, the board shall provide the applicant with written reasons for the disapproval. If the application is approved with conditions, the board shall include in the written decision a detailed description of all conditions necessary to obtain final approval.

 

673:16, III

(Publication of Fees)

8/23/22

None

II. Any fee which a city or town imposes on an applicant pursuant to this title shall be published in a location accessible to the public during normal business hours. Any fee not published in accordance with this paragraph at the time an applicant submits an application shall be considered waived for purposes of that application. A city or town may comply with the requirements of this section by publicly posting a list of fees at the city or town hall or by publishing a list of fees on the city or town's Internet website.

 

 

 

RSA

Effective Date

Previous Language

New or Revised Language

676:4I(c)

(Planning Board Timeline)

1/01/23

4.06     The Board shall, within 30 days or at the next public meeting for which notice can be given, review the application for completeness as required by these Regulations. If the application is determined to be complete and all required fees have been paid,  then the Board shall by motion accept the application as complete relative to the jurisdiction of the Board per RSA 676:4 i(b) and begin formal consideration of the application

 

            If the Board finds the application to be incomplete, the subdivider shall be notified of the deficiencies in writing. The Board may reject an application with no further action based upon failure to supply information required by the Regulations, failure to meet reasonable deadlines established by the Board, or failure to pay cost of notice or other fees required by the Board.

 

            The Planning Board will approve, conditionally approve or disapprove within 65 days after formal acceptance in accordance with RSA 676:4.  Conditional approval shall become final without further public hearing upon certification to the Planning Board of compliance with the conditions imposed, provided however, that the conditions meet the requirements of RSA 676:4.  All other conditions require a public hearing.

 

  1. The board shall, at the next regular meeting or within 30 days following the delivery of the application, for which notice can be given in accordance with the requirements of subparagraph (b), determine if a submitted application is complete according to the board's regulation and shall vote upon its acceptance. Upon determination by the board that a submitted application is incomplete according to the board's regulations, the board shall notify the applicant of the determination in accordance with RSA 676:3, which shall describe the information, procedure, or other requirement necessary for the application to be complete. Upon determination by the board that a submitted application is complete according to the board's regulations, the board shall begin formal consideration and shall act to approve, conditionally approve as provided in subparagraph (i), or disapprove within 65 days, subject to extension or waiver as provided in subparagraph (f). In the case of a determination by the board that the application is a development of regional impact requiring notice in accordance with RSA 36:57, III, the board shall have an additional 30 days to act to approve, conditionally approve, as provided in subparagraph (i), or disapprove. If the board determines that it lacks sufficient information to make a final decision on an application and the applicant does not consent to an extension pursuant to subparagraph (f), the board may, in its discretion, deny the application without prejudice, in which case the applicant may resubmit the same or a substantially similar application. If the planning board does not act on the application within that 65-day time period, then the selectmen or city council shall certify on the applicant's application that the plat is approved pursuant to this paragraph. Such a certification, citing this paragraph, shall constitute final approval for all purposes including filing and recording under RSA 674:37 and 676:18, and court review under RSA 677:15.
  2. Failure of the selectmen or city council to certify approval of the plat upon the planning board's failure to act within the required time period shall constitute grounds for the superior court, upon petition of the applicant, to issue an order approving the application. The superior court shall act upon such a petition within 30 days. If the court determines that the failure of the selectmen or the city council to act was not justified, the court may order the municipality to pay the applicant's reasonable costs, including attorney's fees, incurred in securing such order.

 

676:4 I(f)

(90 Day Extension Eliminated)

8/23/22

4.10     The Planning Board may apply to the Selectmen for an extension not to exceed an additional 90 days before acting to approve or disapprove an application.  The applicant may waive the requirement for Planning Board action within the time periods specified in Section 4.06 and consent to such extension as may be mutually agreeable

The applicant may waive the requirement for planning board action within the time periods specified in subparagraph (c) and consent to such extension as may be mutually agreeable.

673:3, I

(Written Findings)

8/23/22

None

The local land use board shall issue a final written decision which either approves or disapproves an application for a local permit and make a copy of the decision available to the applicant. The decision shall include specific written findings of fact that support the decision. Failure of the board to make specific written findings of fact supporting a disapproval shall be grounds for automatic reversal and remand by the superior court upon appeal, in accordance with the time periods set forth in RSA 677:5 or RSA 677:15, unless the court determines that there are other factors warranting the disapproval. If the application is not approved, the board shall provide the applicant with written reasons for the disapproval. If the application is approved with conditions, the board shall include in the written decision a detailed description of all conditions necessary to obtain final approval.

 

673:16, III

(Publication of Fees)

8/23/22

None

II. Any fee which a city or town imposes on an applicant pursuant to this title shall be published in a location accessible to the public during normal business hours. Any fee not published in accordance with this paragraph at the time an applicant submits an application shall be considered waived for purposes of that application. A city or town may comply with the requirements of this section by publicly posting a list of fees at the city or town hall or by publishing a list of fees on the city or town's Internet website.